[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142947":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142947,799,1,"单选题","双代号时标网络计划中，当某工作之后有虚工作时，则该工作的自由时差为( )。（2013）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","该工作的波形线的水平长度",true,{"key":16,"text":17,"correct":18},"B","本工作与紧后工作间波形线水平长度和的最大值",false,{"key":20,"text":21,"correct":18},"C","本工作与紧后工作间波形线水平长度和的最小值",{"key":23,"text":24,"correct":18},"D","后续所有线路段中波形线中水平长度和的最小值","时标网络计划中应以实箭线表示工作，以虚箭线表示虚工作，以波形线表示工作的自由时差。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]