[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142943":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142943,799,1,"单选题","某单代号网络计划如下图（时间单位：天），其计算工期为（ ）天。（2016）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":18},"B","26",true,{"key":20,"text":21,"correct":14},"C","22",{"key":23,"text":24,"correct":14},"D","24","本题考查的是单代号网络计划的时间参数计算。网络图的关键线路为：A→C→G→H→FIN（或①→③→⑥→⑦→⑧）。总工期为26天。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]