[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142922":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142922,799,2,"多选题","在项目实施阶段，项目总进度应包括（ ）。2017",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目建议书编制进度",false,{"key":16,"text":17,"correct":18},"B","设计工程进度",true,{"key":20,"text":21,"correct":18},"C","招标工作进度",{"key":23,"text":24,"correct":14},"D","项目投产运行工作进度",{"key":26,"text":27,"correct":18},"E","工程施工和设备安装进度","BCE","本题考查的是项目总进度目标论证的工作内容。在项目的实施阶段，项目总进度应包括：（1）设计前准备阶段的工作进度；（2）设计工作进度；（3）招标工作进度；（4）施工前准备工作进度；（5）工程施工和设备安装进度；（6）工程物资采购工作进度；（7）项目动用前的准备工作进度等。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]