[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142915":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142915,799,2,"多选题","下图所示的双代号时标网络计划，执行到第4周末及第10周末时，检查其进度如图前锋线所示，检查结果表明( )。（2012）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","第4周末检查时工作B拖后1周，但不影响工期",false,{"key":16,"text":17,"correct":18},"B","第4周末检查时工作A拖后1周，影响工期1周",true,{"key":20,"text":21,"correct":14},"C","第10周末检查时工作I提前1周，可使工期提前1周",{"key":23,"text":24,"correct":18},"D","第10周末检查时工作G拖后1周，但不影响工期",{"key":26,"text":27,"correct":14},"E","在第5周到第10周内，工作F和工作I的实际进度正常","BD","由图可知，第四周检查时工作A均拖后一周，A处于关键线路所以影响总工期一周。B工作拖后两周，有自由时差一周，影响工期一周。因此选项A错B正确; 关键线路两条 AEHK AFIK。I工作提前一周，不能使另一条关键线路提前，工期不能提前。C错误 G工作拖后一周，后面有自由时差，不影响工期 在第5周到第10周内，没有前锋线，没有实际坚持，所以实际进度无法确定是否正常。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]