[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142911":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142911,799,2,"多选题","某工程双代号网络计划如下图所示(时间单位：天)，图中已标出各项工作的最早开始时间ES和最迟开始时间LS。该计划表明( )。（2012）",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","工作1-3的总时差和自由时差相等",true,{"key":16,"text":17,"correct":14},"B","工作2-6的总时差和自由时差相等",{"key":19,"text":20,"correct":14},"C","工作3-5的总时差和自由时差分别为2和0天",{"key":22,"text":23,"correct":14},"D","工作5-7的总时差和自由时差相等",{"key":25,"text":26,"correct":27},"E","工作2-4和工作3-6均为关键工作",false,"ABCD","总时差=工作的最迟开始时间-最早开始时间，自由时差=紧后工作最早开始时间-最早完成时间。由此计算可得ABCD四项是正确的。 工作2-4不是关键工作",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]