[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142902":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142902,799,1,"单选题","某双代号网络计划如下图所示（时间单位：天），其关键线路有（ ）条。（2016）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",true,{"key":16,"text":17,"correct":18},"B","3",false,{"key":20,"text":21,"correct":18},"C","5",{"key":23,"text":24,"correct":18},"D","4","本题考查的是关键线路和关键工作。关键线路①→②→④→⑤→⑥→⑧→⑨；①→③→④→⑤→⑥→⑧→⑨。 @##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]