[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142892":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142892,799,2,"多选题","（2019年真题）在项目的实施阶段,项目总进度包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","设计工作进度",true,{"key":16,"text":17,"correct":18},"B","可行性研究工作进度",false,{"key":20,"text":21,"correct":14},"C","招标工作进度",{"key":23,"text":24,"correct":14},"D","物资采购工作进度",{"key":26,"text":27,"correct":18},"E","用户管理工作进度","ACD","P116 在项目的实施阶段，项目总进度应包括: (1)设计前准备阶段的工作进度。 (2)设计工作进度。 (3)招标工作进度。 (4)施工前准备工作进度。 (5)工程施工和设备安装进度。 (6)工程物资采购工作进度。 (7)项目动用前的准备工作进度等。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]