[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142891":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142891,799,1,"单选题","（2019年真题）根据项目总进度目标论证的工作步骤,进度计划系统结构分析的紧后工作是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目结构分析",false,{"key":16,"text":17,"correct":14},"B","编制各层进度计划",{"key":19,"text":20,"correct":21},"C","项目的工作编码",true,{"key":23,"text":24,"correct":14},"D","编制总进度计划","P117 建设工程项目总进度目标论证的工作步骤如下: (1)调查研究和收集资料; . (2)项目结构分析; (3)进度计划系统的结构分析; (4)项目的工作编码; (5)编制各层进度计划; (6)协调各层进度计划的关系,编制总进度计划; (7)若所编制的总进度计划不符合项目的进度目标,则设法调整; (8)若经过多次调整,进度目标无法实现,则报告项目决策者。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]