[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142889":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142889,799,2,"多选题","（2020年真题）下列建设工程项目计划中,存在关联关系的进度计划有（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工总进度计划和主体工程进度计划",true,{"key":16,"text":17,"correct":18},"B","主体钢结构施工进度计划和设备安装进度计划",false,{"key":20,"text":21,"correct":18},"C","设计进度计划和维修进度计划",{"key":23,"text":24,"correct":14},"D","项目月度计划和周计划",{"key":26,"text":27,"correct":18},"E","土建施工进度计划和主材供货进度计划","AD","P114-115 由不同周期的进度计划构成的计划系统，包括:（1）5年建设进度计划。（2）年度、季度、月度和旬计划等。 由不同深度的进度计划构成的计划系统，包括:（1）总进度规划（计划）。（2）项目子系统进度规划（计划）。（3）项目子系统中的单项工程进度计划等。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]