[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142884":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142884,799,2,"多选题","（2019年真题）下列工程进度计划系统的构成内容中，属于由不同功能进度计划组成的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工总进度计划、主体工程施工进度计划、钢结构工程施工计划",false,{"key":16,"text":17,"correct":14},"B","设计进度计划、物资采购进度计划、施工管理机构的操作性进度计划",{"key":19,"text":20,"correct":21},"C","业主方的控制性进度计划、项目部的月度进度计划",true,{"key":23,"text":24,"correct":14},"D","企业的年度进度计划、项目部的月度进度计划",{"key":26,"text":27,"correct":21},"E","企业投标的指导性进度计划、项目部的实施性进度计划","CE","P114-115 由不同功能的计划构成进度计划系统,包括: (1)控制性进度规划(计划) ; (2)指导性进度规划(计划) ; (3)实施性(操作性)进度计划等。 A属于由不同深度的计划构成进度计划系统的内容; B属于由不同项目参与方的计划构成进度计划系统的内容; D属于由不同周期的计划构成进度计划系统的内容。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]