[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142883":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142883,799,1,"单选题","（2019年真题）关于项目进度计划和进度计划系统的说法，正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度计划系统由多个进度计划组成，是逐步形成的",true,{"key":16,"text":17,"correct":18},"B","进度计划是实施性的，进度计划系统是控制性的",false,{"key":20,"text":21,"correct":18},"C","业主方编制的进度计划是控制性的，施工方编制的进度计划是实施性的",{"key":23,"text":24,"correct":18},"D","进度计划是项目参与方编制的，进度计划系统是业主方编制的","P114-115 建设工程项目进度计划系统是由多个相互关联的进度计划组成的系统，它是项目进度控制的依据。由于各种进度计划编制所需要的必要资料是在项目进展过程中逐步形成的，因此项目进度计划系统的建立和完善也有一个过程，它是逐步形成的。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]