[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142879":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142879,799,1,"单选题","建设工程项目进度控制工作包括：1编制进度计划;2调整进度计划;3进度目标的分析和论证;4跟踪检查计划的执行情况。其正确的工作程序是( )。（2012）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3-1-4-2",true,{"key":16,"text":17,"correct":18},"B","1-2-3-4",false,{"key":20,"text":21,"correct":18},"C","3-1-2-4",{"key":23,"text":24,"correct":18},"D","4-2-3-1","进度控制是一个动态的管理过程。它包括： (1)进度目标的分析和论证 (2)在收集资料和调查研究的基础上编制进度计划 (3)进度计划的跟踪检查与调整;它包括定期跟踪检查所编制进度计划的执行情况，若其执行有偏差，则采取纠偏措施，并视必要调整进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]