[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142875":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142875,799,2,"多选题","建设工程项目总进度纲要的主要内容包括( )。（2012）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目实施的总体部署",true,{"key":16,"text":17,"correct":18},"B","项目结构分析",false,{"key":20,"text":21,"correct":14},"C","总进度规划",{"key":23,"text":24,"correct":14},"D","确定里程碑事件的计划进度目标",{"key":26,"text":27,"correct":14},"E","总进度目标实现的条件","ACDE","总进度纲要的主要内容包括：1.项目实施的总体部署;2.总进度规划;3.各子系统进度规划;4.确定里程碑事件的计划进度目标;5.总进度目标实现的条件和应采取的措施等。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]