[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142874":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142874,799,1,"单选题","根据建设工程项目总进度目标论证的工作步骤，在完成“项目结构分析”工作之后应立即进行的工作是()。（2013）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","调查研究和收集资料",false,{"key":16,"text":17,"correct":18},"B","进度计划系统的结构分析",true,{"key":20,"text":21,"correct":14},"C","项目的工作编码",{"key":23,"text":24,"correct":14},"D","编制各层进度计划","@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]