[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142872":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142872,799,1,"单选题","将一个子项目进度计划分解为若干个工作项，属于项目总进度目标论证工作的。( )。（2012）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目的结构分析",false,{"key":16,"text":17,"correct":18},"B","进度计划系统的结构分析",true,{"key":20,"text":21,"correct":14},"C","项目的工作编码",{"key":23,"text":24,"correct":14},"D","各层进度计划的关系协调","大型建设工程项目的结构分析是根据编制总进度纲要的需要，将整个项目进行逐层分解，并确立相应的工作目录。其中三级工作任务目录，将每一个子项目分解为若干个工作项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]