[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142865":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142865,799,1,"单选题","某项目部按施工总进度计划、主体工程施工计划、钢筋工程施工计划，构建了承包项目的进度计划系统，则该进度计划系统是按不同（ ）组成的计划系统。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","计划功能",false,{"key":16,"text":17,"correct":14},"B","项目参与方",{"key":19,"text":20,"correct":21},"C","计划深度",true,{"key":23,"text":24,"correct":14},"D","计划周期","本题考查的是建设工程项目进度计划系统的内涵。由不同深度的进度计划构成的计划系统，包括：总进度规划（计划）；项目子系统进度规划（计划）；项目子系统中的单项工程进度计划等。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]