[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142863":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142863,799,1,"单选题","（2020年真题）项目管理机构进行成本核算。核算周期按（ ）确定。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","业主方的具体指示",false,{"key":16,"text":17,"correct":14},"B","合同约定的核算周期",{"key":19,"text":20,"correct":21},"C","规定的会计周期",true,{"key":23,"text":24,"correct":14},"D","项目实际施工周期","P70-73 项目管理机构应按规定的会计周期进行项目成本核算。施工成本核算一般以单位工程为对象，但也可以按照承包工程项目的规模、工期、结构类型、施工组织和施工现场等情况，结合成本管理要求，灵活划分成本核算对象。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]