[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142858":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142858,799,1,"单选题","（2019年真题）建设工程项目施工成本管理是指在保证工期和质量要求的情况下,采用相应管理措施（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","全面分析实际成本的变动状态",false,{"key":16,"text":17,"correct":14},"B","严格控制计划成本的变动范围",{"key":19,"text":20,"correct":21},"C","将实际成本控制在计划范围内",true,{"key":23,"text":24,"correct":14},"D","把计划成本控制在目标范围内","P70-73 成本管理就是要在保证I期和质星满足要求的情况下,采取相应管理措施,包括组织措施、经济措施、技术措施、合同措施,把成本控制在计划范围内,并进步寻求最大程度的成本节约。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]