[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142857":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1142857,799,1,"单选题","（2019年真题）建设工程项目施工成本控制涉及的时间范围是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","从施工准备开始至项目交付使用为止",false,{"key":16,"text":17,"correct":14},"B","从工程投标开始至项目竣工结算完成为止",{"key":19,"text":20,"correct":14},"C","从施工准备开始至项目竣工结算完成为止",{"key":22,"text":23,"correct":24},"D","从工程投标开始至项目保证金返还为止",true,"P70-73 建设工程项目施工成本控制应贯穿于项目从投标阶段开始直至保证金返还的全过程，它是企业全面成本管理的重要环节。成本控制可分为事先控制、事中控制(过程控制)和事后控制。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]