[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142851":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142851,799,1,"单选题","施工成本核算要求的归集“三同步”是指（ ）的取值范围应当一致。（2015）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","形象进度、产值统计、实际成本",true,{"key":16,"text":17,"correct":18},"B","成本预测、成本计划、成本分析",false,{"key":20,"text":21,"correct":18},"C","目标成本、预算成本、实际成本",{"key":23,"text":24,"correct":18},"D","人工成本、材料成本、机械成本","形象进度、产值统计、实际成本归集“三同步” ，即三者的取值范围应是一致的。形象进度表达的工程量、统计施工产值的工程量和实际成本归集所依据的工程量均应是相同的数值。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]