[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142831":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142831,799,1,"单选题","分部分项工程成本分析“三算”对比分析，是指( )的比较。（2013）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预算成本、目标成本、实际成本",true,{"key":16,"text":17,"correct":18},"B","概算成本、预算成本、决算成本",false,{"key":20,"text":21,"correct":18},"C","月度成本、季度成本、年度成本",{"key":23,"text":24,"correct":18},"D","预算成本、计划成本、目标成本","分部分项工程成本分析是对预算成本、目标成本、实际成本的三算对比。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]