[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142821":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142821,799,1,"单选题","某项目在进行资金成本分析时，其计算期实际工程款收入为220万元，计算期实际成本支出为119万元，计划工期成本为150万元，则该项目成本支出率为（ ）。2017",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","30.69%",false,{"key":16,"text":17,"correct":18},"B","54.09%",true,{"key":20,"text":21,"correct":14},"C","68.18%",{"key":23,"text":24,"correct":14},"D","79.33%","本题考查的是专项成本分析方法。成本支出率=计算期实际成本支出\u002F计算期实际工程款收入×100%=119\u002F220×100%=54.09%。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]