[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142817":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142817,799,2,"多选题","某项目成本及成本构成比例数据如下表，正确的有（ ）。（2015）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","成本增加比例最大额是间接成本",true,{"key":16,"text":17,"correct":18},"B","成本降低最多的项目是机械费",false,{"key":20,"text":21,"correct":14},"C","成本节约效益最大的是材料费",{"key":23,"text":24,"correct":14},"D","成本节约做得好的是措施费",{"key":26,"text":27,"correct":14},"E","直接成本增加比例最大的是人工费","ACDE","在降低成本占本项一列中，正值代表成本降低，负值代表成本增加，负值中比例最大的是间接成本-7.37%，因此A正确;在成本降低金额一列中，成本降低为正值，最大的是材料费，因此B错误、C正确;成本节约做得最好的应该为降低成本的比例最大者，即措施费8.1%，D正确;直接成本增加比例最大即降低成本占本项负值最大者为人工费-5.22%，E正确。@##",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]