[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142809":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142809,799,2,"多选题","（2019年真题）施工项目专项成本分析包括（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","月度成本分析",false,{"key":16,"text":17,"correct":14},"B","年度成本分析",{"key":19,"text":20,"correct":21},"C","成本盈亏异常分析",true,{"key":23,"text":24,"correct":21},"D","工期成本分析",{"key":26,"text":27,"correct":21},"E","资金成本分析","CDE","P104-112 针对与成本有关的特定事项的分析,包括成本盈亏异常分析、工期成本分析、资金成本分析等内容。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]