[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142808":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142808,799,1,"单选题","（2019年真题）在项目成本分析的依据中,既可对已经发生的经济活动进行核算,又可对尚未发生的经济活动进行核算的方式是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","会计核算",false,{"key":16,"text":17,"correct":14},"B","成本核算",{"key":19,"text":20,"correct":21},"C","业务核算",true,{"key":23,"text":24,"correct":14},"D","统计核算","P103--104 业务核算的范围比会计、统计核算要广。会计和统计核算一般是对已经发生的经济活动进行核算,而业务核算不但可以核算已经完成的项目是否达到原定的目的、取得预期的效果,而且可以对尚未发生或正在发生的经济活动进行核算,以确定该项经济活动是否有经济效果,是否有执行的必要。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]