[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142807":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142807,799,1,"单选题","（2019年真题）某工程项目进行月(季)度成本分析时，发现属于预算定额规定的“政策性”亏损，则应采取的措施是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","从控制支出着手，把超支额压缩到最低限度",true,{"key":16,"text":17,"correct":18},"B","增加变更收入，弥补政策亏损",false,{"key":20,"text":21,"correct":18},"C","将亏损成本转入下一月(季)度",{"key":23,"text":24,"correct":18},"D","停止施工生产，并报告业主方","P104-112 在成本分析中，若发现人工费、机械费等项目大幅度超支，则应该对这些费用的收支配比关系进行研究，并采取应对措施，防止今后再超支。如果是属于规定的\"政策性\"亏损，则应从控制支出着手，把超支额压缩到最低限度。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]