[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142800":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142800,799,2,"多选题","（2019年真题）某分项工程采用嬴得值法分析得到:已完工作预算费用(BCWP)>计划工作预算费用(BCWS)> 已完工作实际费用(ACWP)，则该工程（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","费用节余",true,{"key":16,"text":17,"correct":14},"B","进度提前",{"key":19,"text":20,"correct":21},"C","费用超支",false,{"key":23,"text":24,"correct":21},"D","进度延误",{"key":26,"text":27,"correct":14},"E","费用绩效指数大于1","ABE","P88-100 根据题意，已完工作预算费用(BCWP) >计划工作预算费用(BCWS）>已完工作实际费用(ACWP）， 费用偏差(CV) =已完工作预算费用(BCWP)-已完工作实际费用(ACWP)，CV>0,费用节余; 进度偏差(SV) =已完工作预算费用(BCWP)计划工作预算费用(BCWS) , SV>0 ,进度提前; 费用结效指数(CPI) =费用绩效数(CPI) =已完工作预算费用(BCWP) ) \u002F已完工作实际费用( ACWP) , CPI >1。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]