[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142799":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142799,799,1,"单选题","（2019年真题）某分项工程月计划完成工程量为3200m2，计划单价为15元\u002Fm2，月底承包商实际完成工程量为2800m2，实际单价为20元\u002Fm2 ，则该工程当月的计划工作预算费用(BCWS)为（）元",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","42000",false,{"key":16,"text":17,"correct":18},"B","48000",true,{"key":20,"text":21,"correct":14},"C","56000",{"key":23,"text":24,"correct":14},"D","64000","P88-100 计划工作预算费用( BCWS ) =计划工作量x预算单价=3200x15=48000元。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]