[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142798":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142798,799,1,"单选题","（2019年真题）应用曲线法进行施工成本偏差分析时，已完工作实际成本曲线与已完工作预算成本曲线的竖向距离表示（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本累计偏差",true,{"key":16,"text":17,"correct":18},"B","进度累计偏差",false,{"key":20,"text":21,"correct":18},"C","进度局部偏差",{"key":23,"text":24,"correct":18},"D","成本局部偏差","P88-100 已完工作实际成本与已完工作预算成本曲线直接的竖向距离,表示的是费用偏差,且是成本累计偏差。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]