[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142791":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142791,799,1,"单选题","施工成本的过程控制中，人工费的控制实行（）方法（2014）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","量化管理",false,{"key":16,"text":17,"correct":18},"B","量价分离",true,{"key":20,"text":21,"correct":14},"C","弹性管理",{"key":23,"text":24,"correct":14},"D","指标包干","人工费的控制实行“量价分离” 的方法，将作业用工及零星用工按定额工日的一定比例综合确定用工数量与单价，通过劳务合同进行控制。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]