[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142788":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142788,799,1,"单选题","某施工项目部根据以往项目的材料实际耗用情况，结合具体施工项目要求，制定领用材料标准控制发料。这种材料用量控制方法是（ ）。（2015）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","定额控制",false,{"key":16,"text":17,"correct":14},"B","计量控制",{"key":19,"text":20,"correct":21},"C","指标控制",true,{"key":23,"text":24,"correct":14},"D","包干控制","在保证符合设计要求和质量标准的前提下，合理使用材料，通过定额控制、指标控制 、计量控制、包干控制等手段有效控制物资材料的消耗。 指标控制：对于没有消耗定额的材料，则实行计划管理和按指标控制的方法。根据以往项目的实际耗用情况，结合具体施工项目的内容和要求，制定领用材料指标，以控制发料。超过指标的材料，必须经过一定的审批手续方可领用。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]