[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142783":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142783,799,1,"单选题","在施工成本的过程控制中，需进行包干控制的材料是（ ）。2017",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","钢钉",true,{"key":16,"text":17,"correct":18},"B","水泥",false,{"key":20,"text":21,"correct":18},"C","钢筋",{"key":23,"text":24,"correct":18},"D","石子","本题考查的是施工成本控制的方法。包干控制。在材料使用过程中，对部分小型及零星材料（如钢钉、钢丝等）根据工程量计算出所需材料量，将其折算成费用，由作业者包干使用。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]