[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142782":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142782,799,1,"单选题","关于建设工程项目施工成本控制的说法。正确的是（ ）。2017",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工成本管理体系由社会有关组织进行评审和认证",false,{"key":16,"text":17,"correct":14},"B","管理行为控制程序是进行成本过程控制的重点",{"key":19,"text":20,"correct":21},"C","施工成本控制可分为事先控制、过程控制和事后控制",true,{"key":23,"text":24,"correct":14},"D","管理行为控制程序和指标控制程序是相互独立的","本题考查的是施工成本控制的步骤。选项A，成本管理体系的建立是企业自身生存发展的需要，没有社会组织来评审和认证。选项B，管理行为控制程序是对成本全过程控制的基础。选项D，管理行为控制程序和指标控制程序既相对独立又相互联系，既相互补充又相互制约。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]