[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142781":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142781,799,2,"多选题","施工成本控制的主要依据包括（ ）。2017",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程承包合同",true,{"key":16,"text":17,"correct":14},"B","施工成本计划",{"key":19,"text":20,"correct":21},"C","施工图预算",false,{"key":23,"text":24,"correct":14},"D","进度报告",{"key":26,"text":27,"correct":14},"E","工程变更","ABDE","本题考查的是施工成本控制的依据。施工成本控制的主要依据包括：工程承包合同；施工成本计划；进度报告；工程变更。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]