[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142779":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142779,799,1,"单选题","某工程项目截至8月末的有关费用数据为：BCWP为980万元，BCWS为820万元，ACWP为1050万元，则其SV为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","-160",false,{"key":16,"text":17,"correct":18},"B","160",true,{"key":20,"text":21,"correct":14},"C","70",{"key":23,"text":24,"correct":14},"D","-70","SV=BCDP-BCWS=已完工作预算费用-计划工作预算费用=160.这个题目是送分题。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]