[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142777":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142777,799,1,"单选题","（2020年真题）下列成本计划中，用于确定责任总成本目标的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","指导性成本计划",true,{"key":16,"text":17,"correct":18},"B","竞争性成本计划",false,{"key":20,"text":21,"correct":18},"C","响应性成本计划",{"key":23,"text":24,"correct":18},"D","实施性成本计划","P74-78 指导性成本计划是选派项目经理阶段的预算成本计划，是项目经理的责任成本目标。它是以合同价为依据，按照企业的预算定额标准制定的设计预算成本计划，且一般情况下以此确定责任总成本目标。 实施性成本计划是项目施工准备阶段的施工预算成本计划，它是以项目实施方案为依据，以落实项目经理责任目标为出发点，采用企业的施工定额通过施工预算的编制而形成的实施性成本计划。 竞争性成本计划是施工项目投标及签订合同阶段的估算成本计划。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]