[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142770":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1142770,799,1,"单选题","（2019年真题）建设工程项目施工成本按构成要素可分解为（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","直接费、间接费、利润、税金等",false,{"key":16,"text":17,"correct":14},"B","单位工程施工成本、分部工程施工成本、分项工程施工成本等",{"key":19,"text":20,"correct":14},"C","人工费、材料费、施工机具使用费、措施项目费等",{"key":22,"text":23,"correct":24},"D","人工费、材料费、施工机具使用费、企业管理费等",true,"P79-80 按照成本构成要素划分，建筑安装工程费由人工费、材料(包含工程设备)费、施工机具使用费、企业管理费、利润、规费和增值税组成。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]