[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142769":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142769,799,1,"单选题","编制施工项目成本计划的关键是确定( )。（2012）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","预算成本",false,{"key":16,"text":17,"correct":14},"B","平均成本",{"key":19,"text":20,"correct":21},"C","目标成本",true,{"key":23,"text":24,"correct":14},"D","实际成本","施工成本计划的编制以成本预测为基础，关键是确定目标成本。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]