[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142766":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142766,799,2,"多选题","某项目实施过程中，绘制了下图所示的时间一成本累计曲线，该图反映的项目程度的正确信息有()（2013）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","I阶段进度慢",false,{"key":16,"text":17,"correct":14},"B","III阶段进度慢",{"key":19,"text":20,"correct":21},"C","II阶段进度慢",true,{"key":23,"text":24,"correct":21},"D","IV阶段进度慢",{"key":26,"text":27,"correct":14},"E","工程施工连续","CD","从图中可以看出施工进度的节奏为第一阶段比较快，第二阶段处于停工状态，第三阶段比较快，第四阶段比较慢",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]