[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142764":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142764,799,2,"多选题","某施工项目为实现成本管理收集可以下资料，其中可以作为编制施工成本计划依据的有（）（2014）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","施工预算",true,{"key":16,"text":17,"correct":14},"B","签订的工程合同",{"key":19,"text":20,"correct":14},"C","分包合同",{"key":22,"text":23,"correct":24},"D","施工图预算",false,{"key":26,"text":27,"correct":14},"E","资源市场价格","ABCE","施工成本计划的编制依据包括 ： ( 1 )投标报价文件 ； ( 2 )企业定额、施工预算； ( 3 )施工组织设计或施工方案 ； ( 4 )人工、材料、机械台班的市场价； ( 5 )企业颁布的材料指导价、企业内部机械台班价格、劳动力内部挂牌价格； ( 6 )周转设备内部租赁价格、摊销损耗标准 ； ( 7 )已签订的工程合同、分包合同（或估价书）； ( 8 )结构件外加工计划和合同 ； ( 9 )有关财务成本核算制度和财务历史资料； (10)施工成本预测资料； (11)拟采取的降低施工成本的措施； (12)其他相关资料 。 @##",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]