[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142761":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1142761,799,1,"单选题","某项目按施工进度编制的施工成本计划入下图，则4月份计划成本是（ ）万元。（2015）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","300",false,{"key":16,"text":17,"correct":14},"B","750",{"key":19,"text":20,"correct":14},"C","1150",{"key":22,"text":23,"correct":24},"D","400",true,"根据时间—成本累积曲线，可以推导出每月的进度计划成本，1150-750=400万元。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]