[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142756":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142756,799,1,"单选题","编制成本计划时，施工成本可以按成本构成分解为（ ）。 (2013)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人工费、材料费、施工机具使用费、规费和企业管理费",false,{"key":16,"text":17,"correct":18},"B","人工费、材料费、施工机具使用费、企业管理费",true,{"key":20,"text":21,"correct":14},"C","人工费、材料费、施工机具使用费、规费和间接费",{"key":23,"text":24,"correct":14},"D","人工费、材料费、施工机具使用费、间接费、利润和税金","施工成本可以按成本构成分解为人工费、材料费、施工机具使用费和企业管理费等。 @##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]