[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142721":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142721,799,2,"多选题","（2019年真题）项目风险管理过程中，项目风险评估包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","分析各种风险的损失量",true,{"key":16,"text":17,"correct":18},"B","确定风险因素",false,{"key":20,"text":21,"correct":18},"C","编制项目风险识别报告",{"key":23,"text":24,"correct":14},"D","分析各种风险因素发生的概率",{"key":26,"text":27,"correct":14},"E","确定各种风险的风险量和风险等级","ADE","P64 1. 利用已有数据资料(主要是类似项目有关风险的历史资料)和相关专业方法分析各种风险因素发生的概率； 2. 分析各种风险的损失量，包括可能发生的工期损失、费用损失,以及对工程的质量、功能和使用效果等方面的影响; 3. 根据各种风险发生的概率和损失量,确定各种风险的风险量和风险等级。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]