[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142715":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142715,799,1,"单选题","下列影响建设工程项目实施的风险因素中，属于技术风险的是( )。（2013）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程勘察资料",true,{"key":16,"text":17,"correct":18},"B","气象条件",false,{"key":20,"text":21,"correct":18},"C","公用防火设施的数量",{"key":23,"text":24,"correct":18},"D","人身安全控制计划","技术风险，如 ： ( 1 ) 工程勘测资料和有关文件； ( 2 ) 工程设计文件； ( 3 ) 工程施工方案； ( 4 ) 工程物资； ( 5 ) 工程机械等。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]