[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142714":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142714,799,1,"单选题","项目风险管理过程包括：1项目风险响应，②项目风险评怙，③项目风险识别，④项目风险控制，其正确的管理流程是( )。（2013）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3214",true,{"key":16,"text":17,"correct":18},"B","3241",false,{"key":20,"text":21,"correct":18},"C","2341",{"key":23,"text":24,"correct":18},"D","1324","风险管理过程括项目实施全过程的项目风险识别、项目风险评估、项目风险响应和项目风险控制。 @##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]