[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142710":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142710,799,2,"多选题","根据《建设工程项目管理规范》GB\u002FT50326-2006，项目风险管理计划应包括（ ）。2017",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","风险分类和风险排序要求",true,{"key":16,"text":17,"correct":14},"B","可使用的风险管理方法、工具",{"key":19,"text":20,"correct":21},"C","确定风险因素",false,{"key":23,"text":24,"correct":21},"D","分析各种风险损失量",{"key":26,"text":27,"correct":21},"E","收集风险信息","AB","本题考查的是项目风险管理的工作流程。项目风险管理计划包括：（1）风险管理目标；（2）风险管理范围；（3）可使用的风险管理方法、工具以及数据来源；（4）风险分类和风险排序要求；（5）风险管理的职责和权限；（6）风险跟踪的要求；（7）相应的资源预算。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]