[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142682":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142682,799,1,"单选题","（2019年真题）项目目标动态控制工作包括:①确定目标控制的计划值，②分解项目目标，③收集项目目标的实际值，④定期比较计划值和实际值，⑤纠正偏差，正确的工作流程是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①③②⑤④",false,{"key":16,"text":17,"correct":18},"B","②①③④⑤",true,{"key":20,"text":21,"correct":14},"C","③②①④⑤",{"key":23,"text":24,"correct":14},"D","①②③④⑤","P48-50 (1)第一步，项目目标动态控制的准备工作:将项目的目标进行分解,以确定用于目标控制的计划值。 (2)第二步，在项目实施过程中项目目标的动态控制: ①收集项目目标的实际值,如实际投资,实际进度等; ②定期(如每两周或每月) 进行项目目标的计划值和实际值的比较; ③通过项目目标的计划值和实际值的比较,如有偏差,则采取纠偏措施进行纠偏。 (3)第三步,如有必要,则进行项目目标的调整。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]