[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142678":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142678,799,2,"多选题","（2019年真题）根据《建筑施工组织设计规范》,施工管理计划包括（）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","进度管理计划",true,{"key":16,"text":17,"correct":14},"B","质量管理计划",{"key":19,"text":20,"correct":14},"C","安全管理计划",{"key":22,"text":23,"correct":24},"D","运营管理计划",false,{"key":26,"text":27,"correct":14},"E","环境管理计划","ABCE","P44-46 《建筑施工组织设计规范》GB\u002FT 50502--2009 对施工管理规划作了如下一些解释和规定。即:施工管理计划应包括进度管理计划、质量管理计划、安全管理计划、环境管理计划成本管理计划以及其他管理计划等内容。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]