[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142677":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142677,799,2,"多选题","根据《建筑施工组织设计规范》（GB\u002FT50502-2009)，以分部（分项）工程或专项工程为主要对象编制的施工方案，其主要内容包括（）。 （2014）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程概况",true,{"key":16,"text":17,"correct":18},"B","施工部署",false,{"key":20,"text":21,"correct":14},"C","施工方法和工艺要求",{"key":23,"text":24,"correct":14},"D","施工准备与资源配置计划",{"key":26,"text":27,"correct":18},"E","施工现场平面布置","ACD","工程概况； ( 2 ) 施工安排； ( 3 ) 施工进度计划； ( 4 ) 施工准备与资源配置计划 ； ( 5 ) 施工方法及工艺要求。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]