[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142676":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1142676,799,1,"单选题","下列项目目标动态控制的纠偏措施中，属于组织措施的是( )。（2012）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","调整进度管理方法",false,{"key":16,"text":17,"correct":14},"B","改变施工管理方法",{"key":19,"text":20,"correct":14},"C","强化合同管理",{"key":22,"text":23,"correct":24},"D","调整工作流程组织",true,"组织措施，分析由于组织的原因而影响项目目标实现的问题，并采取相应的措施，如调整项目组织结构、任务分工、管理职能分工、工作流程组织和项目管理班子人员等 ABC均为管理措施的内容。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]